How to write a project charter (with a template for payments projects)

A charter is not a plan. It is the sponsor's written decision that the project exists, what it must achieve and how much authority the project manager has.

Article
Reading time
8 min read
Sections
8
Published
November 4, 2026
LinkedInEmail
In this essay8 sections

A project charter is a short document, issued by the project sponsor, that formally authorizes a project and gives the project manager authority to use the organization's resources on it. It records why the project exists, what it must achieve, what is in and out of scope, the main milestones and budget, the known risks and constraints, and who can decide what. Write it at the start, keep it to a few pages, and get the sponsor's approval in writing. The template below is built for payments projects, where external certification windows and control owners need a place on the first page.

What is a project charter?

PMI describes the charter as a document issued by the project initiator or sponsor that formally authorizes the project and gives the project manager authority to apply organizational resources to it. PMI's guidance also notes that the sponsor only has to authorize the charter, not write it; the project manager often drafts it. PMI: project charter, what it is and how to write one

The important word is authority. A charter answers three questions: does the sponsor want this project to exist, who leads it, and what can that person decide without going back to the sponsor?

PRINCE2 does not use the term "charter". Its closest equivalents are the project brief, produced when starting up a project, and the project initiation documentation, which the project board reviews before authorizing the project. AXELOS: PRINCE2 project brief · AXELOS: project initiation documentation

How is a charter different from a business case, PRD or project plan?

Document Question it answers Owner Detail level
Business case Is this worth investing in? Sponsor Costs, benefits, options
Project charter Does the project exist, who leads it, with what authority? Sponsor authorizes; project manager drafts A few pages
PRD What exactly should the product do? Product manager Requirements and acceptance
Project plan How and when will the work be done? Project manager Full schedule, resources, risks

The charter points to the others instead of repeating them. The payment program business case guide covers the investment decision and the payments PRD template covers product requirements.

What sections should a project charter include?

PMI's guidance lists the business need, objectives and success criteria, high-level scope, key stakeholders, assumptions and constraints, and the sponsor and project manager, with risks, milestones and approval requirements in a fuller version. PMI: project charter For payments projects, add two fields that are often missed: external gates (scheme, partner or regulator approvals) and control owners (security, compliance, finance).

Project charter template

Copy this table and fill in the right-hand column. If a field cannot be filled, that is a finding: resolve it before work starts.

Section What to write Questions to answer
Project name and ID Short, specific name Would someone outside the team know what this is?
Sponsor One named person Who funds this and can stop it?
Project manager One named person Who is accountable for delivery?
Business need Two or three sentences What problem or opportunity, for whom, and why now?
Objectives Outcomes you can verify at the end How will we know it worked?
Success criteria Measurable acceptance conditions Who accepts, and on what evidence?
In scope Products, markets, channels, payment methods What exactly is included?
Out of scope Explicit exclusions What will people assume is included but is not?
Milestones Key dates, including external gates Which dates are fixed by others?
Budget Approved amount and contingency Who approves spend above it?
External gates Certifications, licenses, partner approvals Who approves, on what evidence, and when?
Constraints Fixed dates, standards, systems, people What cannot change?
Assumptions What is believed but not confirmed What happens if it is wrong?
Key risks Top three to five What could stop or delay the project?
Stakeholders and control owners Names and roles Who must be consulted or must approve?
Project manager's authority Decision limits What can the project manager decide alone?
Approval Signature, date, version Who authorized this and when?

The "out of scope" and "authority" rows prevent most later arguments. Product vision boundaries and non-goals shows how to write exclusions that hold.

A payments integration charter (illustrative)

This example is invented. Names, numbers and dates are illustrative.

Section Example
Project name Second card acquirer for UAE e-commerce merchants
Sponsor Head of Payments Operations
Project manager Named delivery lead
Business need All UAE card volume runs through one acquirer. An outage stops checkout for every merchant in that market.
Objectives Route eligible UAE card transactions to either acquirer; fail over automatically if one is unavailable
Success criteria Certification passed; pilot merchants settle correctly through both acquirers for 30 days (illustrative); operations and finance accept the service
In scope Card-not-present Visa and Mastercard, AED, existing merchants in the UAE
Out of scope Card-present, other markets, new payment methods, pricing changes
Milestones Build complete; acquirer certification window; pilot; general availability (dates illustrative)
Budget Approved amount plus 10% contingency (illustrative)
External gates Acquirer certification; confirmation from compliance on whether any regulatory notification is needed
Constraints Certification window booked by the acquirer; PCI DSS scope must not expand without security approval
Assumptions Acquirer sandbox available from week 2; reconciliation file follows the format in the contract
Key risks Certification slot moves; settlement file differences; routing rules affect authorization rates
Control owners Security (PCI DSS scope), compliance, finance (reconciliation), operations (runbook)
Project manager's authority Re-sequence work within milestones; approve changes up to five days of effort; anything moving a milestone or budget goes to the sponsor
Approval Sponsor, written approval, version 1.0

Two details reflect payments reality. The certification window is listed as an external gate because the acquirer controls it, and the project plans backward from it; payment partner certification covers that work. Compliance is asked a question rather than assumed: whether a change needs regulatory notice depends on the firm's license and the change, so the charter records who will confirm it.

Who writes and who signs the project charter?

The sponsor authorizes the charter. The project manager usually drafts it with the sponsor and key stakeholders. PMI's guidance recommends getting the authorization in writing, even if it is a one-line reply. PMI: project charter

Signatures should match decision rights:

  • Sponsor: always. Without the sponsor's approval, it is a draft.
  • Budget holder: if different from the sponsor.
  • Control owners: acknowledge the constraints that concern them, for example security on PCI DSS scope. They do not approve the project, but they should not first hear of it at launch.
  • Project manager: accepts the role and the authority limits.

In PRINCE2 the equivalent decision sits with the project board, with the executive as the final decision-maker. AXELOS: PRINCE2 roles

What are the most common project charter mistakes?

  1. Objectives that cannot be checked. "Improve resilience" is a wish. "Fail over automatically within the agreed time" can be tested.
  2. No out-of-scope list. Silence on exclusions is read as inclusion. This is where scope creep starts.
  3. Writing the plan in the charter. Detailed task lists date quickly. Keep the charter at milestone level.
  4. No authority limits. If the project manager's decision rights are not written down, every decision escalates or none does.
  5. Signed by the wrong person. A charter approved by someone without budget or authority does not authorize anything.
  6. Ignoring external gates. In payments, the scheme, partner or regulator date often sets the schedule. Leave it out and the plan is fiction.
  7. Never revisited. The charter normally stays in place for the life of the project, but when scope, budget or sponsor changes materially, update it and re-approve the new version.

For where the charter sits among the other initiation steps, see what project management is.

FAQ

What is a project charter?

A short document, issued by the sponsor, that authorizes a project to exist and gives the project manager authority to use resources on it. It records the business need, objectives, scope, milestones, budget and risks.

Who signs a project charter?

The project sponsor, and the budget holder if different. Control owners often acknowledge relevant constraints, and the project manager accepts the role.

How long should a project charter be?

Usually one to a few pages. PMI's guidance describes it as concise and high level; detail belongs in the project plan.

What is the difference between a project charter and a project plan?

The charter authorizes the project and sets its boundaries. The plan describes how and when the work will be done, and changes much more often.

Is a project charter used in agile projects?

Often yes, in a lighter form. Even an agile team needs a sponsor's decision on purpose, boundaries, budget and the fixed external dates it must meet.

Tags
project charterproject charter templateproject initiationproject sponsorpayments projects

Closing thought and further reading

A charter is not a plan. It is the sponsor's written decision that the project exists, what it must achieve and how much authority the project manager has.

Share article
LinkedInEmail
Keep reading
View all essays
Program Management

Scope creep: how to handle change requests without saying no to everything

Change is normal. Scope creep is change nobody priced. Make the cost of each request visible, decide it at the right level, and record the trade-off.

4 min read
Program Management

Payment Partner Certification: A Practical Readiness and Exit Checklist

Certification is a controlled proof that a defined product, version, route, and message set meets a partner's requirements. Track scope and evidence through production release.

5 min read
Program Management

Payment Program Business Cases and Benefits

Compare payment-program options, costs and risks, then build a benefits register with baselines, accountable owners and post-launch measures.

7 min read
Operating proof
Continue the conversation

Need help applying this to your business?

Explore practical support for payment operations, product decisions, program delivery and AI automation, grounded in the challenges behind this essay.

Explore relevant supportEmail Rizwan
Payments Infrastructure Notes

Interested in future field notes?

Request email updates on payments, product decisions, program delivery and practical AI. Your request goes to my inbox for follow-up.

A request for occasional updates, with no weekly schedule promised.